Live from Toast · updated 0 min ago
This week's targets
|
Net sales
$18,502
$4,337 so far
|
Labor hours
258 hrs
60.5 hrs so far
|
Cost of goods
$5,551
Not tracked yet
|
Net sales, labor hours and purchasing for the week, with what has landed so far underneath each. |
Yesterday · Wednesday, Sep 9
Missed forecast by $23
$2,287
$2,310 forecast · −$23 |
Sales: Watch |
99% of yesterday’s goal Forecast from the last 6 Wednesdays |
Labor · Wednesday, Sep 9
Labor was 30.0%, on budget
$686
against a budget of
$686
at $21.50/hr loaded wage · 31.9 hrs worked |
On plan |
100% of the labor budget $2,287 of sales × 30% target ÷ $21.50/hr loaded wage ≈ 31.9 hrs the budget affords. Toast reports $686 in actual wages paid. | Where the day went
| Day part | Sales | Forecast | vs forecast |
| Day | $2,287 | $2,310 | −$23 | | Lunch (11a–2p) | $869 | $878 | −$9 | | Dinner (5p–9p) | $1,418 | $1,432 | −$14 |
| Dinner carried the miss — $14 of the day’s $23 gap. Today
Today · Thursday, Sep 10
$2,583
36.0 labor hrs · $775 of stock it allows |
Forecast |
| The week so far Sales
|
Net sales
through Wednesday Sep 9 |
$4,337 |
|
|
Behind plan
$4,445 was planned by now |
−$108 |
|
|
Remaining 4 days
planned at |
$14,058 |
|
|
To finish the week on plan
what those days now need |
$14,165 |
| A $108 gap over 4 remaining days is $27 a day more than each was already forecast to do. Hourly labor
|
Hours used
through Wednesday Sep 9 · $1,301 of hourly payroll |
60.5 hrs |
|
|
Under budget
$4,337 of sales pays for 60.5 hrs at 30% · $0 under on payroll |
−0.0 hrs |
|
|
Labor % of sales
$1,301 of hourly payroll on $4,337 of sales · target 30% |
30.0% |
|
|
Hours available, last 4 days
49.0 a day — 30% of their $14,058 forecast |
196.2 hrs |
| Staff those days to budget and the week finishes at 30.0% labor. |